Request Quote

Steam Turbine Performance Analysis

[ back to full computer program list ]

American Can Company - Green Bay East Plant
10 MW Steam Turbine Performance Test

Performance Test Analysis (PDF)
Performance Test Analysis with Diagram (PDF)

1. Energy Entering The Steam Turbine Generator Must Be Equal To Energy Leaving

a. Energy Entering The Steam Turbine Generator
(1) Throttle Steam : 264,747,920 Btu/hr

b. Energy Leaving The Steam Turbine Generator
(1) Extraction Steam:
(2) Exhaust Steam:
(3) Electricity:
(4) Mechanical Losses:
(5) Generator Losses:
(6) Total Energy Leaving:
139,096,100.00 Btu/hr
98,900,760.00 Btu/hr
25,464,766.74 Btu/hr (7463 Kw)
535,031.39 Btu/hr
751,261.87 Btu/hr
264,747,920.00 Btu/hr

TURBINE.txt




[ back to full computer program list ]      [ back to top ]

Articles

Methods of Calculating Water Recovery From Air Conditioning Cooling Coils
( PDF Only )

Boiler Analysis ( PDF )

Water Vapor Migration &
Condensation Control in Buildings
( PDF )

Dehumidification ( PDF )

Compressed Air ( PDF )

Cost of Electricity & Air Emissions from Systems ( PDF )

Waterborne Freight Fuel Consumption Efficiency ( PDF )